8 men complete a work in 40 days. How many days will be taken to complete the samed work if 2 more men join them.

Respuesta :

rpband00
rpband00 rpband00
  • 04-04-2018
Hello there,

There were 8 men who completed a task in 40 days. If you divide 40/8 that is 5 so it took them 5 weeks to complete this task.

Now if you add two more men, that makes it 10 men to complete the work in 50 days. If you divide 50/10 that is 5.
10 days

Hope this helped!

Answer Link

Otras preguntas

the area of north dakota is 77,353 square miles. the area of south dakota is 70,700 square miles. how many square miles greater is the area of north dakota than
What is the relationship between gross pay and net pay?
347 cm is equal to: 347 m 34.7 m 3.47 m 0.347 m
9. What is .333 written in its simplest fraction form? A. 1,000/333 B. 1 /3 C. 333/1,000 D. 3 /33 3/33
Which of the following decisions would be helped by understanding science? A) Determining your political stance on human rights B) Determining your political st
How did the Reconquista act as a pull mechanism for Spain to explore and conquer new lands?
What is the ground state configuration of Cr2+, Cu2+ and Co3+?
If f(x)=3x+1 then f(a+h)-f(a)
Which of the following is a key reason to include hyperbole in a literary work? I. to add humor Il. to heighten effect III. to create suspense
Can anyone help with this please